Completed Thousand Oaks pool remodeling project with new Baja shelf and slate stone paver deck
Completed Project · Thousand Oaks, California

Complete Pool Remodeling + New Baja Shelf

A complete Thousand Oaks pool transformation combining an engineered Baja shelf addition with new pool return-line plumbing, a new skimmer, code-compliant split drain, electrical work, patio drainage, custom precast coping, new tile, Mini Pebble plaster, and a slate stone paver pool deck.

$125K Project Range 6–8 Week Timeline Engineering + Permit New Baja Shelf
Location Thousand Oaks, CA
Project Investment $125K Range
Timeline 6–8 Weeks
Project Type Pool Remodel + Baja Addition
Project Overview

More than resurfacing this pool was physically redesigned.

The Thousand Oaks project involved remodeling the existing pool while modifying the pool structure to add a new Baja shelf. That meant coordinating engineering, permitting, demolition, new gunite, circulation plumbing, drainage, electrical work, pool finishes, coping, and the surrounding deck.

New return-line plumbing, a new skimmer, and a split drain installed to code upgraded the pool circulation system. The surrounding outdoor area received a new patio drain system and slate stone pavers over a newly prepared base.

Custom precast coping, new tile, and Mini Pebble plaster completed the water environment after the structural and underground work was finished.

01 New Baja Shelf

Existing pool modified to create a new shallow lounging and entry area.

02 New Pool Systems

New return lines, new skimmer, split drain, and electrical upgrades.

03 Slate Stone Deck

New pool-deck base and slate stone paver installation around the pool.

04 New Finish Package

Custom precast coping, new pool tile, and Mini Pebble plaster.

Before Photos

The existing Thousand Oaks pool before remodeling.

The original pool and deck provided the starting point for a much more extensive transformation that would change both the pool structure and surrounding outdoor surface.

Project Challenges

Modifying an existing pool requires coordinated structural and system upgrades.

Adding a Baja shelf changed the existing pool configuration, while the surrounding circulation, electrical, drainage, deck, coping, and finishes all needed to be rebuilt around it.

01

Baja Shelf Addition

The existing pool shell had to be modified so a new Baja shelf could be integrated into the original water environment.

02

Pool System Upgrades

New return lines, a new skimmer, split-drain plumbing, and electrical work were coordinated with the remodel.

03

Deck & Drainage

The new slate stone pool deck required base preparation and coordination with a new patio drain system.

Demolition & Preparation

Opening the existing pool for structural modification.

Demolition removed the existing materials and exposed the areas needed for pool modification, plumbing, Baja construction, coping, deck work, and new finishes.

Baja Shelf Addition

Changing the way the existing pool can be used.

The Baja shelf was added as a new structural component within the existing pool, creating a shallow area for lounging and easier interaction with the water.

Engineered Pool Modification

Because the remodel changed the physical pool configuration, engineering and permitting were part of the project process.

Baja Gunite

Building the new Baja shelf into the existing pool structure.

Gunite was used to form the new Baja shelf after the pool modification and structural preparation were completed.

Custom Precast Coping

A custom edge around the remodeled pool.

Custom precast coping was installed after the Baja and pool modification work, creating the finished transition between the water and the new deck surface.

Pool Deck Preparation

A new base for the slate stone deck.

The surrounding deck was prepared with a new base before the slate stone pavers were installed, while patio drainage was coordinated into the surrounding hardscape.

Slate Stone Pavers

Rebuilding the deck around the remodeled pool.

Slate stone pavers were installed around the pool to create a new deck surface that works with the custom coping, Baja shelf, pool finishes, and patio drainage system.

Plaster Preparation

Preparing the remodeled pool for its final interior finish.

After structural modification, plumbing, coping, tile, and related construction were completed, the pool shell was prepared for the Mini Pebble finish.

Mini Pebble Plaster

The final interior finish.

Mini Pebble plaster completes the remodeled pool interior and the newly constructed Baja shelf.

Materials & Systems

Selected for this Thousand Oaks project

  • Mini Pebble pool plaster
  • Custom precast pool coping
  • New pool tile
  • Slate stone deck pavers
  • New pool return-line plumbing
  • New skimmer
  • Split drain installed to code
  • Electrical work
  • New patio drain system
  • New Baja shelf gunite
Scope of Work

Complete permitted pool modification

  • Engineering coordination
  • Permit process
  • Existing pool demolition
  • Pool structure modification
  • New Baja shelf construction
  • Baja gunite installation
  • New return-line plumbing
  • New skimmer installation
  • Code-compliant split drain
  • Electrical work
  • Patio drainage system
  • Custom precast coping installation
  • New pool tile
  • Pool deck base preparation
  • Slate stone paver installation
  • Plaster preparation
  • Mini Pebble plaster installation
Exclusive Design Method

The 3-Zone System™

The 3-Zone System™ helps us consider how the pool, deck, circulation, lounging areas, and surrounding outdoor environment work together instead of treating each feature as an isolated improvement.

Learn About the 3-Zone System™ →
01

Arrival Zone™

Circulation through the outdoor area influences how homeowners and guests approach and move around the pool deck.

02

Living Zone™

The slate stone paver deck creates usable space around the pool for seating, lounging, conversation, and everyday outdoor living.

03

Activity Zone™

The remodeled pool and new Baja shelf become the central activity area for swimming, lounging, cooling off, and relaxing.

Project Investment & Timeline

Project planning at a glance.

These figures describe this specific Thousand Oaks project. Similar projects vary based on pool condition, structural modifications, engineering, permitting, plumbing, deck area, materials, and total construction scope.

Project Range $125K

Baja shelf modification, pool systems, coping, tile, plaster, slate stone deck, drainage, engineering, and permit work.

Construction Timeline 6–8 Weeks

Pool demolition, structural modification, Baja construction, plumbing, hardscape, finishes, and completion.

Project Process Engineered + Permitted

Engineering and permitting were part of the project because the existing pool structure was modified.

After Photos

The completed Thousand Oaks pool transformation.

The completed project combines the new Baja shelf, upgraded pool circulation, custom precast coping, new tile, Mini Pebble plaster, slate stone pavers, patio drainage, and updated pool systems into one coordinated outdoor environment.

Completed Thousand Oaks pool remodel with new Baja shelf
Completed Pool + Baja Shelf
Finished Thousand Oaks pool and slate stone deck
Finished Pool Environment
Thousand Oaks Pool Remodeling FAQ

Questions about projects like this one.

These answers describe this Thousand Oaks case study. Every pool renovation has different structural, permit, plumbing, drainage, finish, and site requirements.

What was included in this Thousand Oaks pool remodel?

The project included engineering and permitting, demolition, modification of the existing pool, construction of a new Baja shelf, Baja gunite, new pool return-line plumbing, a new skimmer, split drain installed to code, electrical work, a patio drainage system, custom precast coping, new pool tile, Mini Pebble plaster, base preparation, and slate stone paver installation.

Was a Baja shelf added to the existing pool?

Yes. The existing pool was structurally modified so a new Baja shelf could be added.

Did the project require engineering and permits?

Yes. Engineering and permitting were included because the project involved modification of the existing pool structure and construction of the new Baja shelf.

What plumbing upgrades were completed?

The remodel included new pool return-line plumbing, a new skimmer, and a split-drain configuration installed to code.

What type of pool deck was installed?

A new deck base was prepared and slate stone pavers were installed around the remodeled swimming pool.

What pool finish was used?

Mini Pebble plaster was installed as the final interior pool finish.

What was the investment range for this Thousand Oaks project?

This project was completed in approximately the $125,000 range. Similar projects vary based on structural modifications, engineering, permitting, pool size, plumbing, deck area, materials, drainage, and total scope.

How long did the project take?

The construction timeline was approximately 6–8 weeks. Other projects may vary depending on permits, inspections, engineering, structural work, materials, and site conditions.

Build Up Remodeling

Want to change more than the finish of your existing pool?

We can help evaluate the pool structure, Baja shelf possibilities, circulation, plumbing, drainage, coping, tile, plaster, pool deck, and surrounding outdoor environment to determine the right remodeling scope for your property.